Rejoose includes predefined UPS loss and cooling overheads based on ‘The green grid maturity model’.

The default setting is “level 2 – Best practice” from the maturity model.

If you have knowledge about the cooling ad UPS installation, we recommend adjusting it. See the following tips:

  • Choose among predefined cooling overhead and UPS loss for your current and future installation.
  • If you have knowledge about the exact cooling overhead and UPS loss fill out custom values.
  • If UPS or Cooling is not directly affected/changes in your project, the overheads/losses should be the same level on current and future installation.
  • If there’s no UPS or cooling, set these to 0%.

When done, click ‘Save’ and ‘Continue’, which presents you for report options.